Builders

How to Quote a Bathroom Renovation in Australia

A bathroom is a small room hiding a lot of trades. Here's how to quote a bathroom renovation so waterproofing, plumbing and the hidden nasties are all priced before you commit to a number.

A bathroom is the smallest room in the house and the easiest one to lose money on. Demolition, waterproofing, plumbing, tiling, electrical and fit-off all crammed into a few square metres, plus whatever's rotting behind the old wall sheet. The quotes that hurt are the ones that priced the tiles and forgot the rest. This guide covers what a bathroom quote should include, what it costs in 2026, and the mistakes that quietly eat your margin.

What a good bathroom quote covers

A bathroom touches more trades than almost any room its size. Before you price anything, make sure the scope lists every one of these:

  • Demolition and waste removal — stripping the old room out and getting the rubble off site.
  • Waterproofing — a compliant membrane to AS 3740, priced as its own line, not buried in the tiling.
  • Tiling — floor and walls, with the tile, adhesive, grout and waste factor spelled out.
  • Plumbing — rough-in and fit-off, plus any relocation of the toilet, shower or vanity.
  • Electrical — lighting, exhaust fan, power points and often a heated towel rail.
  • Fixtures and fittings — vanity, toilet, shower screen, tapware and accessories.
  • Structural and sheeting work — any framing repairs, new wall sheet or gyprock.

Write the quote as line items with clear inclusions and exclusions. A bathroom is where a vague 'supply and install bathroom' turns into an argument at handover — spell out exactly what the client is getting.

Bathroom renovation costs in 2026

A standard bathroom renovation in Australia lands between $15,000 and $35,000, driven by size, finish and how much the plumbing moves. Quote materials at today's prices — tiles, membrane, adhesive and tapware all move, and last month's numbers will cost you.

Bathroom renovation cost by tier (supply and install)
TierTypical costWhat it looks like
Budget$10,000–$15,000Like-for-like layout, standard tiles and off-the-shelf fixtures
Mid-range$20,000–$30,000Some relocation, quality tiles, framed screen and a decent vanity
High-end$40,000+New layout, premium tiles and tapware, frameless screen, feature lighting

Add a 10% waste factor on tiles and adhesive — cuts, breakages and pattern-matching all eat into the box count, and running short mid-job means a second delivery and a stalled tiler.

Working out labour

The cleanest way to price bathroom labour is by trade and by day, then total it. A typical mid-range bathroom runs to roughly two working weeks once you allow for drying time between stages:

  • Demolition — 1–2 days to strip and cart away.
  • Plumbing rough-in — around a day, more if you're relocating fixtures.
  • Waterproofing — a day to apply, plus curing time before anyone tiles.
  • Tiling — 2–4 days depending on tile size, floor prep and wall coverage.
  • Plumbing fit-off and electrical — roughly a day and a half combined.
  • Finishing — silicone, screen, accessories and the final clean.

If you're subcontracting the plumber, tiler or sparky, add your margin on top of their price — you carry the coordination, the risk and the callbacks, and that's worth charging for.

Waterproofing and compliance

Waterproofing is where a bathroom either lasts twenty years or leaks in two, and it's the compliance line most likely to bite you. Price it properly and put it in writing.

  • Wet areas must be waterproofed to AS 3740 — this is not the place to cut corners or blend the cost into tiling.
  • In many states waterproofing must be done or certified by a licensed applicator; check your local requirements before you quote.
  • Allow for the membrane to fully cure before tiling — that drying time is real days on the program, not a pause.
  • Homes built before the late 1980s can hide asbestos in sheeting and old floors; factor testing and licensed removal where it's a risk.

Common mistakes that eat your margin

  1. Under-pricing the waterproofing. Compliant membrane and a licensed applicator cost real money. Buried inside a tiling rate, it quietly comes out of your margin.
  2. Underestimating demo and waste. Stripping a bathroom back to frame is slow, and skip bins and tip fees add up. Price the demolition and the rubbish removal as their own lines.
  3. Missing plumbing relocations. Moving a toilet or shower a metre means new rough-in and often floor work. Confirm the layout before you price, not after.
  4. Quoting off last month's tile prices. Tile, adhesive and tapware prices move. Pull current supplier pricing the day you quote so the numbers still hold when the job starts.
  5. No contingency for hidden damage. Rotten framing, old wiring and asbestos live behind the wall sheet. A 5–10% contingency line covers the surprises without a difficult variation conversation.

Pro tips for a bathroom quote that holds

  • Always inspect the existing bathroom in person before you quote — you're pricing what's behind the tiles as much as what's on them.
  • Break the quote into sections: demo, waterproofing, tiling, plumbing, electrical and fixtures.
  • State inclusions and exclusions plainly so there's no argument over who's supplying the tapware.
  • Add the 5–10% contingency as a visible line, not a hidden buffer.
  • Pull current material prices the day you quote.
  • Include payment terms and a realistic timeline that allows for curing days.

ServiceYak keeps your tiling, waterproofing, plumbing and fit-off rates in a reusable kit, so you can build an itemised bathroom quote on site and send the PDF before you've left the driveway.

Frequently asked questions

How much does a bathroom renovation cost in Australia?

A standard renovation runs $15,000–$35,000 supplied and installed. Budget like-for-like jobs start around $10,000–$15,000, while a high-end bathroom with premium tiles, tapware and a new layout can push past $40,000.

Does the waterproofing have to meet a standard?

Yes — wet areas must be waterproofed to AS 3740, and in many states the work must be done or certified by a licensed applicator. Price it as its own line and allow curing time before tiling.

How long does a bathroom renovation take?

Most mid-range bathrooms run around two working weeks. The trades themselves are quick, but demolition, waterproofing cure time and drying between stages stretch the program more than people expect.